House Addition- Week 1 & 2

We started construction on a 2 story addition to an existing single story house.  By ‘we,’ I mean the general contractor, a few guys and me.  I’m actually on-site most days getting dirty, learning new things and trying not to get hurt.

20090803-002

SITE: Here is the back of the house along the alley.

20090803-005


Step 1.  Demolish existing garage - BEFORE

20090803-008

during…

20090803-013

AFTER - note the water line that snakes up and down.  Easy to understand why they have low water pressure.

STEP 2- Demolish concrete driveway and diffuse a near neighborhood revolt by agreeing to start (noisy) work later in the morning.

20090817-028

Step 3: Reroute water heater to side of the house and spend a few days in the crawlspace piping water, heat and electricity accordingly.

What I learned: Watch your head.  Eat a real breakfast before construction work.  Bend back nails.  No jackhammers before 9am.  How to sweat copper pipes.  Pipe wrenches are amazing.  Avoid mummified rats in the crawlspace.  Think ahead.

"House Addition- Week 1 & 2" was published on September 15th, 2009 and is listed in Uncategorized.

Follow comments via the RSS Feed | Leave a comment | Trackback URL

Leave Your Comment





About Us | People | Recent Work | Archived Work | Contact | Blog | Client Log-In

© 2008 CHU+GOODING Architects. All Rights Reserved.